Converted · legalization · Outer Mission

706 Huron Ave

Completed Nov 2024+1 unit on this lot · now 24 permits

To legalize unauthorized unit on first flr per covernment code sec 6582. 2 with two bedrooms. One bathrm, kitchen & living/dining area. Exterior deck & rear stairs.

filed Jan 2022issued Apr 2024 · permit wait 2 years 4 monthscompleted Nov 2024 · built in 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$200,000
declared on the ADU permit
Permit wait
2 years 4 months
filed → issued
Build time
6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitTo legalize unauthorized unit on first flr per covernment code sec 6582. 2 with two bedrooms. One bathrm, kitchen & living/dining area. Exterior deck & rear stairs.
202201115776 · S M Construction And Associates INC
filed Jan 2022 · issued Apr 2024 · done Nov 2024$200kcity record
ElectricalLegalize unit on 1/f, 2 bedrooms, 1 bath, 1 kitchen and living/diing area. Exterior deck repair, electrical work: rewire new unit and install new service overhead. 3-0 feeder, 1 subpanel 200 amp. 6 circuits, 10 lights, 6 switches, 20 receptacles, 1 fan, 1 g/d, 1 microwave, 1 range, 3 s/d. Fridge. Ufer ground work.
E202405024133
May 2, 2024 → Aug 30, 2024—
PlumbingNew bathroom and kitchen at first floor as per approved pa# 202201115776. Repair existing waste lines for bathroom and kitchen at 2/f. Fabracated shower pan and underground work.
PP20240502638
May 2, 2024 → Sep 3, 2024—
PlumbingInstall new furance for ADU unit. New bathroom fan, new tankless water heater, exhaust line for kitchen hood.
PM20240612339
Jun 12, 2024 → Sep 3, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 7101A, lot 002
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map