Converted · West of Twin Peaks

70A Terrace Dr

Completed May 2024+1 unit on this lot · now 15 permits

Convert existing free-standing garage to an ADU studio unit including adding new bathroom, kitchen, closet, living room & platform. Per ordinance 95-17.

filed Dec 2022issued Oct 2023 · permit wait 9 monthscompleted May 2024 · built in 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$76,500
declared on the ADU permit
Permit wait
9 months
filed → issued
Build time
7 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert existing free-standing garage to an ADU studio unit including adding new bathroom, kitchen, closet, living room & platform. Per ordinance 95-17.
202212309516 · S F Town Builders INC
filed Dec 2022 · issued Oct 2023 · done May 2024$77kcity record
ElectricalUpgrade main house panel. Add subpanel in ADU. Power for d/w, with d, range and hood. Outlets and switches, ceiling lights. 8 lighs, 5 switches, 10 receptalces, 2 fans, 1 d/w, 1 g/d, 1 range, 1 s/d.
E202310069951
Oct 6, 2023 → Apr 16, 2024—
Electrical200 amp 2, meter service change.
EW202404158016
Apr 15, 2024 → Jul 15, 2025—
PlumbingAdd new heat pump for ADU, 1 kitchen hood.
PM20231006395
Oct 6, 2023 → Apr 15, 2024—
PlumbingNew bathroom in ADU, new water heater, with d, new kitchenette. One shower pan, underground work included.
PP20231006394
Oct 6, 2023 → Apr 15, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 3072A, lot 023
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map