Converted · ground-floor conversion · Lone Mountain/USF

719A Spruce St

Completed Feb 2025+1 unit on this lot · now 34 permits

Convert 1/f of unit #1 into a new ADU utilizing the ca. State ADU program per gov. Code sec. 65852. 2; ADU will have new kitchen, living-eating area, sleeping alcove & bath. Unit will retain existing windows & existing sep. Electric heat source. Note: this work is in addition to approved pa# 202310108258.

filed Jan 2024issued Sep 2024 · permit wait 9 monthscompleted Feb 2025 · built in 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$30,000
declared on the ADU permit
Permit wait
9 months
filed → issued
Build time
5 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert 1/f of unit #1 into a new ADU utilizing the ca. State ADU program per gov. Code sec. 65852. 2; ADU will have new kitchen, living-eating area, sleeping alcove & bath. Unit will retain existing windows & existing sep. Electric heat source. Note: this work is in addition to approved pa# 202310108258.
202401033389 · Alfa Building Solutions INC
filed Jan 2024 · issued Sep 2024 · done Feb 2025$30kcity record
ElectricalRef to building pa# 202401033389 at garage level unit: remodel 1 kitchen & 1 bathroom, replace e) sub penal, 14 circuits, 60 amp.
E202411138199
Nov 13, 2024 → Jan 30, 2025—
ElectricalElectrical work for garage level unit: remodel 1 kitchen and 1 bathroom. Replace existing existing subpanel, 14 circuits, 60 amp. Ref to existing electrical permit# e202411138199.
E202501309705
Jan 30, 2025 → Jan 30, 2025—
PlumbingRemodel 1 kitchen & 1 bathroom at garage level unit.
PP20241113034
Nov 13, 2024 → Jan 29, 2025—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1087, lot 001A
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map