Converted · ground-floor conversion · Outer Mission

73 Seminole Ave

In progress+1 unit on this lot · now 21 permit

Ordinance 95-17. Remodel & new ADU for single family house. 1st floor new ADU, 2nd floor remodel, new bedroom, bath, new stairs.

filed Mar 2020issued Apr 2022 · permit wait 2 years 2 months4 years 6 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$70,000 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
2 years 2 months
filed → issued
Build time
in progress
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitOrdinance 95-17. Remodel & new ADU for single family house. 1st floor new ADU, 2nd floor remodel, new bedroom, bath, new stairs.
202003025929
filed Mar 2020 · issued Apr 2022$70kcity record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6971B, lot 004
Why we call it an ADU
SF DBI flagged the permit as an ADU.