Converted · ground-floor conversion · Bernal Heights

74 Gladys St

Completed Dec 2025+1 unit on this lot · now 49 permits

Provide new ADU (1, 146 sq ft) at unconditioned basement and ground floor.

filed Dec 2022issued Apr 2024 · permit wait 1 year 5 monthscompleted Dec 2025 · built in 1 year 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$393,925
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
1 year 5 months
filed → issued
Build time
1 year 7 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitProvide new ADU (1, 146 sq ft) at unconditioned basement and ground floor.
202212017468 · Rinaldi Construction Co INC
filed Dec 2022 · issued Apr 2024 · done Dec 2025$354kcity record
SprinklersRef pa # 22-1201-7468 provide a nfpa 13 fire sprinkler systeim in the basement ground floor entry for new ADU (20 sprinklers). Provide new 2" fire service (21 feet).
202408158701 · Fire Guard Protection INC
filed Aug 2024 · issued Aug 2024$26kcity record
SprinklersSprinkler waterflow & supervisory system, install new control panel, radio communicator, smoke detector & pull station on ground floor, install monitor modules to tie-in flow & tamper to be monitor. Ref # 202408158701.
202408279558 · Fire & Security & Alarm Co
filed Aug 2024 · issued Aug 2024 · done May 2025$14kcity record
ElectricalRewiring receptacle outlets, wall switches and ceiling light s for of 2 bedrooms one bathroom, one kitchen and one living room and installation of subpanel.
EW202411072335
Nov 7, 2024 → Apr 21, 2025—
ElectricalRewiring of whole apartment with one kitchen, two bathrooms, two bedrooms and one living room and a subpanel.
EW202412102928
Dec 10, 2024 → Apr 21, 2025—
ElectricalOnline electrical permit: 60 of buildings of 6 dwelling units or less. Sprinkler monitoring system.
E202505202565
May 20, 2025 → May 29, 2025—
Plumbing74c: install 4 indoor fan coils in the ceiling. 74d: install 3 indoor fan coils in the ceiling and install 1 new multiport heat pump outside.
PM20241205403
Dec 5, 2024 → Mar 28, 2025—
PlumbingWork category: 4pa; install fire sprinkler in ADU at first basement level only, 2" fire service from from valve to riser location.
PW20241205548
Dec 5, 2024 → May 29, 2025—
PlumbingRenew pp20230410384: to obtain final inspection.
PP20250513208
May 13, 2025 → May 19, 2025—
1 other permit on this lot during the project, not counted
OtherTo obtain final inspection for work approved under pa#202205174449 all work is complete.
202511048842
filed Nov 2025 · issued Nov 2025 · done Nov 2025—city record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 5712, lot 016
Why we call it an ADU
SF DBI flagged the permit as an ADU.