In progress+1 unit on this lot · now 24 permits

New ADU unit per ordinance #162-16. Add kitchen, family room, (2) bedrooms & (1) full bathroom. Horizontal addition @ rear under separate permit appln #201811155981.

filed Dec 2019issued Oct 2024 · permit wait 4 years 10 months2 years 1 month since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$50,000
declared on the ADU permit
Permit wait
4 years 10 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitNew ADU unit per ordinance #162-16. Add kitchen, family room, (2) bedrooms & (1) full bathroom. Horizontal addition @ rear under separate permit appln #201811155981.
201912200237 · C H T Properties Development
filed Dec 2019 · issued Oct 2024$50kcity record
Related permitTo obtain final inspection for work approved under pa# 201912200237. All work is complete.
202607235490 · cites 201912200237 · C H T Properties Development
filed Jul 2026 · issued Jul 2026 · done Jul 2026—city record
ElectricalAdd 1 subpanel and new electrical wiring to a new addition. (16 lights, 6 switches, 20 receptacles, 1fan and 4 smoke detectors).
E202505122382
May 12, 2025 → Jan 21, 2026—
PlumbingAdd 1 bathroom with underground plumbing in new addition. 1 shower pan.
PP20250512202
May 12, 2025 → Jan 21, 2026—
1 other permit on this lot during the project, not counted
OtherTo obtain final inspection for work approved under pa# 201811155981. All work is complete.
202607235481 · C H T Properties Development
filed Jul 2026 · issued Jul 2026 · done Jul 2026—city record

Trade permits show what work was done and when; the city does not record who pulled them.