Converted · ground-floor conversion · West of Twin Peaks

80A Entrada Ct

In progress+1 unit on this lot · now 22 permits

(unit a) new ADU on ground floor (972 sq ft), per ca gov code sec 65852. 2. Add 2 bedrooms, 2 bathrooms, living room & kitchen on existing ground floor install plywood wall reinforcement for voluntary ground floor structural strengthening. Partial new foundation, reinforce & underpinning existing footing.

filed Jan 2024issued Jul 2025 · permit wait 1 year 5 months1 year 4 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$264,365
declared on the ADU permit
Permit wait
1 year 5 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permit(unit a) new ADU on ground floor (972 sq ft), per ca gov code sec 65852. 2. Add 2 bedrooms, 2 bathrooms, living room & kitchen on existing ground floor install plywood wall reinforcement for voluntary ground floor structural strengthening. Partial new foundation, reinforce & underpinning existing footing.
202401264778 · Curran And Associates General Contractors INC
filed Jan 2024 · issued Jul 2025$264kcity record
PlumbingUnderground plumbing, in wall rough plumbing, new sewer pipes, rought plumning for sink and shower, kitchen sink.
PP20260812815
Aug 12, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6917A, lot 024
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map