Converted · garage conversion · Lone Mountain/USF
828 Anza St
Completed Aug 2024+4 units on this lot · now 1611 permits
(4) ground floor accessory dwelling units in existing garage spaces. Infill (2) garage doors along anza street and add (2) wood windows at front facade. Ref pa#2016/1108/2366 completed soft story retrofit. Required ground floor fire sprinkler and full building fire alarm system under deferred p.
filed Nov 2020issued Feb 2023 · permit wait 2 years 3 monthscompleted Aug 2024 · built in 1 year 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$466,028 for 4 ADUs
one permit, 4 units; not a per-unit price
Permit wait
2 years 3 months
filed → issued
Build time
1 year 6 months
issued → completed
Builder
No contractor listed
Also on this project: All Star Fire Protection LLC, Crime Watch Security Sys Llc
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | (4) ground floor accessory dwelling units in existing garage spaces. Infill (2) garage doors along anza street and add (2) wood windows at front facade. Ref pa#2016/1108/2366 completed soft story retrofit. Required ground floor fire sprinkler and full building fire alarm system under deferred p. 202011108672 | filed Nov 2020 · issued Feb 2023 · done Aug 2024 | $379k | city record |
| Sprinklers | Install new fire sprinkler system throughout ground floor building per nfpa 13-r including 2" dedicated fire service per nfpa 24. Ref permit 202011108672. 202305097419 · cites 202011108672 · All Star Fire Protection LLC | filed May 2023 · issued May 2023 · done Apr 2024 | $35k | city record |
| Related permit | Upgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1. 202305248498 · Crime Watch Security Sys Llc | filed May 2023 · issued May 2023 · done Apr 2024 | $52k | city record |
| Electrical | 4 kitchen and 4 bathroom. EW202303229877 | Mar 22, 2023 → Feb 22, 2024 | — | |
| Electrical | Rewire kitchen and bath room unit 102. EW202304200502 | Apr 20, 2023 → Mar 7, 2024 | — | |
| Electrical | Rewire kitchen and bath room for unit 103. EW202304200503 | Apr 20, 2023 → Feb 22, 2024 | — | |
| Electrical | Rewire kitchen and bathroom for unit 104. EW202304200504 | Apr 20, 2023 → Feb 22, 2024 | — | |
| Electrical | Modification of exisiting fire alarm to comply with sffc 1103. 7. 6. EW202306282176 | Jun 28, 2023 → Mar 29, 2024 | — | |
| Plumbing | Work category: 2pb; 4 kitchen and 4 bathroom. PW20230322635 | Mar 22, 2023 → Feb 8, 2024 | — | |
| Plumbing | Work category: 2pa; install new heat. PW20230328794 | Mar 28, 2023 → Feb 21, 2024 | — | |
| Plumbing | This pays for inspections related to original permit # pp20230512918 filed 5/12/2023. Dow: work category: 4pa; report date: 3/25/2024 12: 25: 34 pm application number: pp20230512918 address(es): 1085 / 038: 828 anza st description: install new fire sprinklers throughtout ground floor including 2' dedicated service. PW20240325575 | Mar 25, 2024 → Mar 29, 2024 | — |
These permits also cite 201611082366, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1085, lot 038
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.