Converted · ground-floor conversion · Nob Hill
828 Taylor St
Completed Nov 2023+1 unit on this lot · now 107 permits
Addition of one ADU unit at the ground floor per the state ADU program for a total of 10 units. Within existing envelope.
filed Jun 2022issued Feb 2023 · permit wait 8 monthscompleted Nov 2023 · built in 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$98,713
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
8 months
filed → issued
Build time
10 months
issued → completed
Builder
Doherty Restoration INCAlso on this project: O'Connor Plumbing & Fire Protection INC, Crime Watch Security Sys Llc
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Addition of one ADU unit at the ground floor per the state ADU program for a total of 10 units. Within existing envelope. 202206065707 · Doherty Restoration INC | filed Jun 2022 · issued Feb 2023 · done Nov 2023 | $60k | city record |
| Related permit | Provide f/s protection for new ADU only 10 heads. Ref 202206065707. 202305198151 · cites 202206065707 · O'Connor Plumbing & Fire Protection INC | filed May 2023 · issued May 2023 · done Oct 2023 | $15k | city record |
| Related permit | Upgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1. 202308255295 · Crime Watch Security Sys Llc | filed Aug 2023 · issued Aug 2023 · done Oct 2023 | $23k | city record |
| Electrical | #a: electrical work for one ADU, 1 bed and 1 bath, studio unit. E202305036612 | May 3, 2023 → Jul 31, 2023 | — | |
| Electrical | Modification of an existing fire alarm system by upgrading the fire panel, update all existing devices to be compatible with new facp and provide low frequency sounders in all sleeping areas to meet 75db at pillow to comply with sffd bulletin 1103. 7. 6. 1. EW202306232033 | Jun 23, 2023 → Oct 10, 2023 | — | |
| Plumbing | Plumbing work for one new ADU, include underground rough and finish for 1 studio bath with shower pan. PP20230503763 | May 3, 2023 → Jul 28, 2023 | — | |
| Plumbing | Work category: 4pa; provide fire sprinkler system for new ADU only on ground floor. Tie in to existing sprinkler system. PW20230522206 | May 22, 2023 → Oct 25, 2023 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 0274, lot 014
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.