Converted · ground-floor conversion · West of Twin Peaks

883 Urbano Dr

Completed Aug 2022+1 unit on this lot · now 24 permits

New ADU at ground level. Lower the first floor to create an 8' floor to ceiling height for the proposed ADU.

filed Jan 2021issued Nov 2021 · permit wait 10 monthscompleted Aug 2022 · built in 9 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$100,000
declared on the ADU permit
Permit wait
10 months
filed → issued
Build time
9 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitNew ADU at ground level. Lower the first floor to create an 8' floor to ceiling height for the proposed ADU.
202101202963 · A J O Group Build INC
filed Jan 2021 · issued Nov 2021 · done Aug 2022$100kcity record
ElectricalG/f ADU, under approved pa# 202101202963.
E202112077189
Dec 7, 2021—
PlumbingGround floor ADU, under approved pa# 202101202963.
PP20211207871
Dec 7, 2021 → Jul 27, 2022—
PlumbingWork category: 1m; lower unit: installation of new mitsubishi heat pump system with new condensate drain line for lower unit.
PMW20220705878
Jul 5, 2022 → Jul 14, 2022—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6922, lot 006
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map

Converted · ground-floor conversion ADU at 883 Urbano Dr · MiCasa