Detached · Inner Sunset

89 Belgrave Ave

Completed Nov 2024+1 unit on this lot10 permits

To erect a 2-story, type vb, 1-unit ADU structure at rear.

filed Nov 2022issued Aug 2023 · permit wait 9 monthscompleted Nov 2024 · built in 1 year 3 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$452,847
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
9 months
filed → issued
Build time
1 year 3 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitTo erect a 2-story, type vb, 1-unit ADU structure at rear.
202211156492 · 5 Elements Design And Construction
filed Nov 2022 · issued Aug 2023 · done Nov 2024$375kcity record
SprinklersRear ADU building: installation of overhead fire sprinklers system per nfpa13, sprinklers to be installed throughout the entire ADU per approved building pa# 202211156492.
202309146549 · cites 202211156492 · Control Fire INC
filed Sep 2023 · issued Sep 2023 · done Sep 2024$76kcity record
Related permitRef pa# 202309146549 & 201805250168 addition of a new waterflow switch in ADU. Use existing approved system to monitor.
202403278683 · Fox Security & Communications INC
filed Mar 2024 · issued Mar 2024 · done Nov 2024$1,500city record
SprinklersInstallation of overhead fire sprinkler system per nfpa b. Sprinklers to be installed throughout the entire ADU per approved building permit# 202211156492. Revision 1 added 1 head and shifted underground line. As built reference fire permit# 202309146549.
202403288790 · cites 202211156492 · Control Fire INC
filed Mar 2024 · issued Mar 2024 · done Nov 2024—city record
RevisionRevision to previous permit# 202211156492: revised mechanical mini-split unit and revised t-24 energy report.
202407166599 · cites 202211156492 · Kadon Construction INC
filed Jul 2024 · issued Jul 2024 · done Nov 2024—city record
ElectricalWire new ADU.
EW202310254730
Oct 25, 2023 → Sep 19, 2024—
ElectricalADU sprinler flow & bell connect to existing approved system.
E202403273370
Mar 27, 2024 → Nov 5, 2024—
PlumbingWork category: 4pa; installing a new fire sprinkler system.
PW20240312260
Mar 12, 2024 → Apr 2, 2024—
PlumbingWork category: 2pb; provide new plumbing for ADU with 1 full bathroom and kitchen with heat pump water heater.
PW20240312275
Mar 12, 2024 → Aug 27, 2024—
PlumbingInstallation of 1 shower pan.
PP20240411306
Apr 11, 2024 → Apr 15, 2024—

These permits also cite 201805250168, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2688, lot 072
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map