Converted · ground-floor conversion · Haight Ashbury
915 Haight St
Completed Mar 2023+1 unit on this lot · now 35 permits
Change of occupancy; 1 new ADU at ground floor, per state ADU program.
filed Dec 2021issued Sep 2022 · permit wait 9 monthscompleted Mar 2023 · built in 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$80,000
declared on the ADU permit
Permit wait
9 months
filed → issued
Build time
5 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Change of occupancy; 1 new ADU at ground floor, per state ADU program. 202112164579 | filed Dec 2021 · issued Sep 2022 · done Mar 2023 | $80k | city record |
| Revision | As-built to f/s permit 202101283568. 202302011142 · All Star Fire Protection LLC | filed Feb 2023 · issued Feb 2023 · done Feb 2023 | — | city record |
| Plumbing | Work category: 1p; reason of get this permit to finalize the two expired permit pw20201202806 and pw20210331119 for final plumbing. PW20221012657 | Oct 12, 2022 → Jan 19, 2023 | — | |
| Plumbing | Work category: 1p; replaced existing tankless water heaters with more efficient units. PW20221102271 | Nov 2, 2022 → Nov 18, 2022 | — | |
| Plumbing | Work category: 4pa; completly new fire sprinklrs to garage and 3rd floor unit including a 2" dedicated service. PW20230117020 | Jan 17, 2023 → Feb 9, 2023 | — |
These permits also cite 202101283568, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1240, lot 035
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.