Converted · garage conversion · Mission

983 Capp St

Completed Feb 2024+1 unit on this lot · now 18 permits

Rear building add unit per ord 162-17. Add 1 ADU-1 bedroom unit at the existing rear detached garage, with a new kitchen and a new bath.

filed Dec 2019issued Jul 2022 · permit wait 2 years 6 monthscompleted Feb 2024 · built in 1 year 8 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$175,131
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
2 years 6 months
filed → issued
Build time
1 year 8 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitRear building add unit per ord 162-17. Add 1 ADU-1 bedroom unit at the existing rear detached garage, with a new kitchen and a new bath.
201912311057 · Als Builders Pro INC
filed Dec 2019 · issued Jul 2022 · done Feb 2024$130kcity record
SprinklersF/s installation per nfpa 13r/2016. Ref bpa #201912230412, #202207158593, #202207158592, #202207158591.
202210265164 · Professional Fire Safety INC
filed Oct 2022 · issued Nov 2022 · done Nov 2023$29kcity record
Sprinklers2" combo (fire and domestic) water service for domestic water and nfpa 13r system #202210265164 by others. Nfpa 24.
202303012811 · Arch Plumbing INC
filed Mar 2023 · issued Oct 2023 · done Jan 2025$16kcity record
ElectricalUpgrade main electrical system 400 amp single phase underground. Wire in for additional 4- ADU units on ground floor, uffer grounding,.
EW202208055155
Aug 5, 2022 → Nov 21, 2023—
ElectricalRefer to building app. # 201912311053 wire in for ADU b&c.
EW202304110283
Apr 11, 2023—
ElectricalPermission for a 1201 breaker for a fire alarm. 1 circuit.
E20231113584
Nov 13, 2023 → Dec 4, 2023—
PlumbingResidential ground floor sprinkler installation.
PP20221114105
Nov 14, 2022 → Oct 27, 2023—
PlumbingWork category: 2pb; installation of 2 inch copper k combo service for fire and domestic.
PW20231018955
Oct 18, 2023 → Oct 27, 2023—
2 other permits on this lot during the project, not counted
OtherStructural revision to approved permit 201912300957. New concrete foundation & wood framing.
202207158591 · Als Builders Pro INC
filed Jul 2022 · issued Jul 2022 · done Dec 2023—city record
OtherStructural revision to approved permit 201912311053.
202207158592 · Als Builders Pro INC
filed Jul 2022 · issued Jul 2022 · done Dec 2023—city record

These permits also cite 201912230412, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6518, lot 016
Why we call it an ADU
SF DBI flagged the permit as an ADU.