Detached · Bayview Hunters Point

989 Hollister Ave

Completed Mar 2024+1 unit on this lot12 permits

To erect a type-v, 1-story single family ADU in rear of existing building per ADU ordinance 162-17.

filed Feb 2021issued Feb 2022 · permit wait 1 yearcompleted Mar 2024 · built in 2 years 1 month
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$77,780
declared across 4 permits: the ADU permit plus its sub-permits
Permit wait
1 year
filed → issued
Build time
2 years 1 month
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitTo erect a type-v, 1-story single family ADU in rear of existing building per ADU ordinance 162-17.
202102114463 · Castle Company
filed Feb 2021 · issued Feb 2022 · done Mar 2024$55kcity record
SprinklersInstallation of nfpa 13d fire sprinkler system on new ADU; underground on separate permit.
202206297360 · Firemex Solutions INC
filed Jun 2022 · issued Nov 2022 · done Nov 2023$6,720city record
SprinklersRevision to pa# 2021-0211-4463 to indicate rear ADU building to be fully sprinklered per nfpa13d.
202208110333 · cites 202102114463 · Castle Company
filed Aug 2022 · issued Aug 2022 · done Mar 2024—city record
Related permit2" combinatin underground.
202212239128 · Firemex Solutions INC
filed Dec 2022 · issued Dec 2022 · done Feb 2024$16kcity record
Related permitAs builts for pa# 2022-1223-9128; underground with a 2" dedicated fire service.
202301120071 · Firemex Solutions INC
filed Jan 2023 · issued Jan 2023 · done Feb 2024$100city record
ElectricalUpgrade main electrical panel, install new subpanel for new ADU. Run new dedicated lines for new kitchen & bathroom.
E202208302163
Aug 30, 2022 → Aug 24, 2023—
ElectricalResidential pv solar, tilt roof mount, grid tied. - 6 roof-mounted solar pv modules, 400 watts per module, 1 interactive inverter, total no. Of rating 2. 4 kw.
EW202209085907
Sep 8, 2022 → Oct 5, 2023—
ElectricalAdministrative permit for ew202209085907: address correction: 991 hollister not 989 hollister- work completed.
E20231027339
Oct 27, 2023 → Oct 31, 2023—
PlumbingRun new drain and water line to new ADU in backyard. New toilet, vanity, tub, new kitchen sink. Water heater. With underground.
PP20220830812
Aug 30, 2022 → Feb 21, 2024—
PlumbingWork category: 2pa; ADU plumbing @ 1 full bathroom; 1 kitchen sink and 1 water heater.
PW20221011637
Oct 11, 2022 → Jul 19, 2023—
PlumbingInstallation of fire sprinkler system, 4 sprinker head, ADU only.
PP20221104977
Nov 4, 2022 → Mar 1, 2024—
Plumbing2" combinatin underground.
PP20221223744
Dec 23, 2022 → Feb 27, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.