Applied General Construction INC

License #1092591 · activelicensed since 2022Bbased in San Franciscobond $25kworkers’ comp: carrier

Named as contractor on 1 ADU project in San Francisco (and 30 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 ground-floor conversion
Declared cost (middle half)
$210k
median $210k
Build time
1 year 6 months
median, issued → completed
Open · finished
0 · 1

Their ADU projects

  1. 366 24th AveOuter Richmond
    Converted · ground-floor conversionCompleted7 permitsdeclared $210k
    filed Nov 2019permit 4 years 11 monthsbuilt 1 year 6 months · done Apr 2026
    ADU permit 201911278376 · city record · flagged ADU by SF DBI

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.