Bolter Construction

License #463620 · contr bond susplicensed since 1984B, C10, C36based in San Franciscobond $25kworkers’ comp: exemptnot on Yelp

Named as contractor on 1 ADU project in San Francisco (and 5 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 interior conversion
Declared cost (middle half)
$127k
median $127k
Build time
—
median, issued → completed
Open · finished
1 · 0

Their ADU projects

  1. 733 Fillmore StHayes Valley
    Converted · interior conversionPermit issued, in progress7 permitsdeclared $127k
    filed Jul 2019permit 4 years 6 months2 years 10 months since issue
    ADU permit 201907105536 · city record · identified from permit text, two reviewers agree

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.