Michael Carroll Construction INC

License #1015963 · activelicensed since 2016Bbased in San Franciscobond $25kworkers’ comp: carrier

Named as contractor on 2 ADU projects in San Francisco (and 29 permits of any kind). Verify at CSLB before hiring.

ADU projects
2
1 garage conversion · 1 ground-floor conversion
Declared cost (middle half)
$130k–$231k
median $180k
Build time
1 year 1 month
median, issued → completed
Open · finished
0 · 2

Their ADU projects

  1. 2550 Ulloa StSunset/Parkside
    Converted · garage conversionCompleted6 permitsdeclared $281k + other work
    filed Mar 2023permit 7 monthsbuilt 11 months · done Sep 2024
    ADU permit 202303214119 · city record · flagged ADU by SF DBI
  2. 1757 10th AveInner Sunset
    Converted · ground-floor conversionCompleted6 permitsdeclared $80k
    filed Jan 2020permit 1 year 8 monthsbuilt 1 year 2 months · done Nov 2022
    ADU permit 202001303187 · city record · flagged ADU by SF DBI

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.