Globus Builder INC

License #961380 · activelicensed since 2011Bbased in Campbellbond $25kworkers’ comp: carrier

Named as contractor on 1 ADU project in San Francisco (and 5 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 garage conversion
Declared cost (middle half)
$71k
median $71k
Build time
1 year 6 months
median, issued → completed
Open · finished
0 · 1

Their ADU projects

  1. 780 Darien WayWest of Twin Peaks
    Converted · garage conversionCompleted4 permitsdeclared $71k
    filed Jun 2022permit 1 year 5 monthsbuilt 1 year 6 months · done May 2025
    ADU permit 202206307477 · city record · flagged ADU by SF DBI

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.