J R P Design And Construction

Named as contractor on 1 ADU project in San Francisco (and 1 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 attached addition
Declared cost (middle half)
$337k
median $337k
Build time
—
median, issued → completed
Open · finished
0 · 0

Their ADU projects

  1. 16 De Long StOuter Mission
    AttachedCancelled2 permitsdeclared $337k + other work
    filed Oct 2022permit 1 year 10 months2 years 3 months since issue
    ADU permit 202210144379 · city record · flagged ADU by SF DBI

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.