Lordan Construction

License #599290 · activelicensed since 1990Bbased in San Franciscobond $25kworkers’ comp: exemptnot on Yelp

Named as contractor on 1 ADU project in San Francisco (and 10 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 ground-floor conversion
Declared cost (middle half)
$207k
median $207k
Build time
2 years 3 months
median, issued → completed
Open · finished
0 · 1

Their ADU projects

  1. 4416A 20th StCastro/Upper Market
    Converted · ground-floor conversionCompleted16 permitsdeclared $207k + other work
    filed Apr 2021permit 1 year 1 monthbuilt 2 years 3 months · done Jul 2024
    ADU permit 202104027850 · city record · flagged ADU by SF DBI

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.