Named as contractor on 1 ADU project in San Francisco (and 1 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 ADU
Declared cost (middle half)
$285k
median $285k
Build time
—
median, issued → completed
Open · finished
1 · 0

Their ADU projects

  1. 1090 Randolph StOceanview/Merced/Ingleside
    ADU, type not statedPermit issued, in progress4 permitsdeclared $285k + other work
    filed Sep 2022permit 2 years 10 months1 year 3 months since issue
    ADU permit 202209233085 · city record · flagged ADU by SF DBI

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.