Metro General Construction Inc
License #1039728 · not in CSLB's current listworkers’ comp: carrier
Named as contractor on 1 ADU project in San Francisco (and 17 permits of any kind). Verify at CSLB before hiring.
ADU projects
1
1 garage conversion
Declared cost (middle half)
$704k
median $704k
Build time
1 year 11 months
median, issued → completed
Open · finished
0 · 1
Their ADU projects
- 140 Duboce AveMissionConverted · garage conversionCompleted15 permitsdeclared $704k for 4 ADUsfiled Mar 2020permit 1 year 11 monthsbuilt 1 year 11 months · done Dec 2023ADU permit 202003116820 · city record · flagged ADU by SF DBI
Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.