R M Remodeling INC
Named as contractor on 1 ADU project in San Francisco (and 16 permits of any kind). Verify at CSLB before hiring.
ADU projects
1
1 ground-floor conversion
Declared cost (middle half)
$65k
median $65k
Build time
1 year 3 months
median, issued → completed
Open · finished
0 · 1
Their ADU projects
- 1605 Fulton StLone Mountain/USFConverted · ground-floor conversionCompleted4 permitsdeclared $65kfiled Sep 2021permit 2 monthsbuilt 1 year 3 months · done Feb 2023ADU permit 202109178699 · city record · identified from permit text, two reviewers agree
Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.