License #1133321 · activelicensed since 2025Bbased in Daly Citybond $25kworkers’ comp: carriernot on Yelp
Named as contractor on 1 ADU project in San Francisco (and 2 permits of any kind). Verify at CSLB before hiring.
ADU projects
1
1 ground-floor conversion
Declared cost (middle half)
$214k
median $214k
Build time
6 months
median, issued → completed
Open · finished
0 · 1
Their ADU projects
- 474A Waller StHayes ValleyConverted · ground-floor conversionCompleted4 permitsdeclared $214kfiled Jan 2025permit 11 monthsbuilt 6 months · done Jun 2026ADU permit 202412247386 · city record · flagged ADU by SF DBI