Weis & Son
Named as contractor on 1 ADU project in San Francisco (and 2 permits of any kind). Verify at CSLB before hiring.
ADU projects
1
1 ADU
Declared cost (middle half)
$136k
median $136k
Build time
6 months
median, issued → completed
Open · finished
0 · 1
Their ADU projects
- 2111 18th StPotrero HillConvertedCompleted4 permitsdeclared $136kfiled Feb 2022permit 12 daysbuilt 6 months · done Aug 2022ADU permit 202202178233 · city record · identified from permit text, two reviewers agree
Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.