Converted · garage conversion · Noe Valley

128 Vicksburg St

In progress+1 unit on this lot · now 16 permits

Convert existing detached garage (legal non-conforming structure) into an ADU.

filed Feb 2021issued Oct 2024 · permit wait 3 years 8 months2 years 1 month since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$212,000
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
3 years 8 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert existing detached garage (legal non-conforming structure) into an ADU.
202102195046 · High Level Construction And Painting INC
filed Feb 2021 · issued Oct 2024$200kcity record
SprinklersInstall a new fire sprinkler system for the new ADU. Ref pa # 2021-0219-5046.
202509125187 · cites 202102195046 · J & C Safety 1st Fire Protection INC
filed Sep 2025 · issued Sep 2025$12kcity record
ElectricalNew ADU 1 bedroom including kitchen & bathroom.
E202503211124
Mar 21, 2025 → May 8, 2026—
ElectricalRevision to e202503211124: add to job scope; change electrical seek minisplits. Electric heated floors underneath bathroom only.
E202506093072
Jun 9, 2025—
PlumbingFire sprinkler system install at new ADU.
PP20251002027
Oct 2, 2025—
PlumbingTo renew pp20250321242: plumbing for 1 bedroom ADU.
PP20260507963
May 7, 2026 → May 11, 2026—
1 other permit on this lot during the project, not counted
OtherTo obtain final inspection for work approved under pa# 202505075998. All work is complete.
202606183500
filed Jun 2026 · issued Jun 2026—city record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 3652, lot 003
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map