License #1083040 · activelicensed since 2021B, C33based in Oaklandbond $25kworkers’ comp: carrierYelp4.5(19 reviews)

Named as contractor on 1 ADU project in San Francisco (and 4 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 garage conversion
Declared cost (middle half)
$212k
median $212k
Build time
—
median, issued → completed
Open · finished
1 · 0

Their ADU projects

  1. Converted · garage conversionPermit issued, in progress6 permitsdeclared $212k
    filed Feb 2021permit 3 years 8 months2 years 1 month since issue
    ADU permit 202102195046 · city record · flagged ADU by SF DBI