Converted · ground-floor conversion · Mission
1522 Howard St
Completed May 2023+1 unit on this lot · now 74 permits
Application for ADU in existing ground floor space. New work to include new kitchen, remodel of existing bathroom, and new doors and window out to rear yard. Mep, and any required title 24 calcs, permitted separately. Per ord 162-16.
filed Aug 2020issued Oct 2021 · permit wait 1 year 2 monthscompleted May 2023 · built in 1 year 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$120,000
declared on the ADU permit
Permit wait
1 year 2 months
filed → issued
Build time
1 year 7 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Application for ADU in existing ground floor space. New work to include new kitchen, remodel of existing bathroom, and new doors and window out to rear yard. Mep, and any required title 24 calcs, permitted separately. Per ord 162-16. 202008151923 · Jing Hua Construction Corp | filed Aug 2020 · issued Oct 2021 · done May 2023 | $120k | city record |
| Electrical | Remodel ADU at the basement ground floor. Install subpanel. E202203319333 | Mar 31, 2022 → May 12, 2023 | — | |
| Plumbing | Remodel ADU at the basement ground floor. Install back to back gas wall heater, one for bedroom and one for kitchen. Install moisture fan inside full bathroom. PM20220331044 | Mar 31, 2022 → May 11, 2023 | — | |
| Plumbing | Remodel ADU at the basement ground floor. Install water and sewer pipe for a full bathroom and the kithen. PP20220331043 | Mar 31, 2022 → May 11, 2023 | — |
Trade permits show what work was done and when; the city does not record who pulled them.