Jing Hua Construction Corp

License #1021356 · not in CSLB's current listworkers’ comp: carriernot on Yelp

Named as contractor on 1 ADU project in San Francisco (and 4 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 ground-floor conversion
Declared cost (middle half)
$120k
median $120k
Build time
1 year 7 months
median, issued → completed
Open · finished
0 · 1

Their ADU projects

  1. Converted · ground-floor conversionCompleted4 permitsdeclared $120k
    filed Aug 2020permit 1 year 2 monthsbuilt 1 year 7 months · done May 2023
    ADU permit 202008151923 · city record · flagged ADU by SF DBI

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.