Converted · ground-floor conversion · Mission
3675 24th St
Completed Dec 2023+1 unit on this lot · now 84 permits
Construct one accessory dwelling unit (ADU) per state requirements at the 1st floor to replace existing laundry and a portion of the crawl space.
filed Dec 2022issued Aug 2023 · permit wait 8 monthscompleted Dec 2023 · built in 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$158,000
declared on the ADU permit
Permit wait
8 months
filed → issued
Build time
4 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Construct one accessory dwelling unit (ADU) per state requirements at the 1st floor to replace existing laundry and a portion of the crawl space. 202212218914 · Manzyuk Enterprises INC | filed Dec 2022 · issued Aug 2023 · done Dec 2023 | $158k | city record |
| Electrical | Interior remodel for ADU. 10 lights, 6 switches, 10 receptacles, 2 fans, 1 d/w, 1 g/d, 1 microwave, 3 s/d. E202308309071 | Aug 30, 2023 | — | |
| Plumbing | Furnace and duckwork and kitchen & bathroom fans. PM20230830746 | Aug 30, 2023 → Oct 18, 2023 | — | |
| Plumbing | New bathroom and kitchen with underground work. PP20230830745 | Aug 30, 2023 → Oct 18, 2023 | — |
Trade permits show what work was done and when; the city does not record who pulled them.