Manzyuk Enterprises INC
Named as contractor on 1 ADU project in San Francisco (and 29 permits of any kind). Verify at CSLB before hiring.
ADU projects
1
1 ground-floor conversion
Declared cost (middle half)
$158k
median $158k
Build time
4 months
median, issued → completed
Open · finished
0 · 1
Their ADU projects
- 3675 24th StMissionConverted · ground-floor conversionCompleted4 permitsdeclared $158kfiled Dec 2022permit 8 monthsbuilt 4 months · done Dec 2023ADU permit 202212218914 · city record · flagged ADU by SF DBI
Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.