Converted · ground-floor conversion · Castro/Upper Market

4300 17th St

Completed Mar 2024+1 unit on this lot · now 314 permits

Addition of one ADU unit at the first floor under the state ADU program.

filed Mar 2022issued Jul 2022 · permit wait 4 monthscompleted Mar 2024 · built in 1 year 9 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$258,000
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
4 months
filed → issued
Build time
1 year 9 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAddition of one ADU unit at the first floor under the state ADU program.
202203149894 · Actually Design Build INC
filed Mar 2022 · issued Jul 2022 · done Mar 2024$250kcity record
ADU permitRevsion to pa# 2022-0314-9894, intent to comply with 2022 ca code and delete fire sprinklers work scope. And revise occupancy change from r-2 to r-3, (two units + 1 ADU).
202301099846
filed Jan 2023 · issued Aug 2023 · done Mar 2024—city record
RevisionRevision to 202203149894 remove and replace sog. Substitute psl beam for w10x22.
202208311637 · cites 202203149894 · Actually Design Build INC
filed Aug 2022 · issued Aug 2022 · done Mar 2024$8,000city record
ElectricalNew 400amp /120/240v / single phase / 4 meter overhead service. Rebuild/refeed top floor 200a subpanel(unit a) install new 100a subpanel(unit b). Install new 100a subpanel for ground floor (unit c). Wiring/circuits for new "ADU' unit on ground floor (unit c).
EW202208255611
Aug 25, 2022—
ElectricalUnit a- rebuild/resupply existing 200amp subpanel. Refeed existing circuits.
EW202302219197
Feb 21, 2023 → May 3, 2024—
ElectricalUpgrade existing two meter / 200amp electrical service to 400amp four meter service ( including one house meter). Refeed existing stairway lighting.
EW202302219194
Feb 21, 2023 → Mar 21, 2024—
ElectricalUnit b -rebuild/resupply existing 100amp subpanel. Resupply existing circuits. Provide new circuits and outlets for washer and dryer.
EW202302219198
Feb 21, 2023—
ElectricalUnit c - new "ADU" unit. New 100amp subpanel. Kitchen, bathroom, bedroom, and living room. All new wiring throughout.
EW202302219199
Feb 21, 2023 → Feb 9, 2024—
ElectricalTemporary electrical service.
EW202304090246
Apr 9, 2023—
PlumbingNew bathroom with shower, toilet and vanity sink. Island sink for kitchen. Gas line, relocate water heater and some underground pipeing. Shower pan and 3 laundries.
PP20220819632
Aug 19, 2022 → Feb 2, 2024—
PlumbingWork category: 1m; install mini-split heat pump system.
PMW20230802989
Aug 2, 2023 → Aug 23, 2023—
PlumbingWork category: 1p; swap out cabinets, new sink.
PW20230815387
Aug 15, 2023 → Mar 21, 2024—
PlumbingWork category: 1m; this permit is to extend expired permit #pmw20221017800.
PMW20240129224
Jan 29, 2024 → Jan 31, 2024—
PlumbingWork category: 1m; this permit is to extend the expired permit #pmw20221102257.
PMW20240131284
Jan 31, 2024 → Feb 1, 2024—
3 other permits on this lot during the project, not counted
OtherIn kind kitchen remodel.
202208050011
filed Aug 2022 · issued Aug 2022 · done May 2024$21kcity record
OtherExterior stairs and mems of egress for 2nd floor fire safety.
202212158470
filed Dec 2022 · issued Jan 2023$5,000city record
OtherRemove interior load bearing wall.
202212168480
filed Dec 2022 · issued Mar 2023 · done May 2024$5,000city record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2626, lot 014A
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map