Actually Design Build INC

License #1015230 · activelicensed since 2016B, C-8based in San Franciscobond $25kworkers’ comp: carrier

Named as contractor on 3 ADU projects in San Francisco (and 71 permits of any kind). Verify at CSLB before hiring.

ADU projects
3
3 ground-floor conversion
Declared cost (middle half)
$189k–$352k
median $258k
Build time
1 year 3 months
median, issued → completed
Open · finished
1 · 2

Their ADU projects

  1. 422 Funston AveInner Richmond
    Converted · ground-floor conversionCompleted4 permitsdeclared $120k + other work
    filed Jul 2025permit 2 monthsbuilt 9 months · done Jun 2026
    ADU permit 202506249351 · city record · flagged ADU by SF DBI
  2. 4300 17th StCastro/Upper Market
    Converted · ground-floor conversionCompleted14 permitsdeclared $258k
    filed Mar 2022permit 4 monthsbuilt 1 year 9 months · done Mar 2024
    ADU permit 202203149894 · city record · flagged ADU by SF DBI
  3. 566 20th AveOuter Richmond
    AttachedPermit issued, in progress8 permitsdeclared $445k + other work
    filed Feb 2021permit 11 months4 years 11 months since issue
    ADU permit 202102044033 · city record · identified from permit text, two reviewers agree

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.