Converted · ground-floor conversion · Castro/Upper Market

85A Burnett Ave

Completed Mar 2026+1 unit on this lot · now 23 permits

Convert entire first floor into ADU, remove internal circular stair from 1st flr to 2nd flr. Infill flr/clg where stair removed. No other work is required to convert existing space into an ADU. Note: entire 1st flr was existing, unconditioned space prior to 2012. Space was completely built out into.

filed Sep 2025issued Nov 2025 · permit wait 2 monthscompleted Mar 2026 · built in 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$59,425
declared on the ADU permit
Permit wait
2 months
filed → issued
Build time
4 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert entire first floor into ADU, remove internal circular stair from 1st flr to 2nd flr. Infill flr/clg where stair removed. No other work is required to convert existing space into an ADU. Note: entire 1st flr was existing, unconditioned space prior to 2012. Space was completely built out into.
202508253800 · Metro Construction INC
filed Sep 2025 · issued Nov 2025 · done Mar 2026$59kcity record
ElectricalInstall 2 recessed lights, inspection of existing conditions for ADU application.
EW202511211042
Nov 21, 2025 → Dec 12, 2025—
PlumbingWork category: 2pa; legalize the kitchen sink, convert the existing space into a ADU.
PW20251119690
Nov 19, 2025 → Dec 15, 2025—

Trade permits show what work was done and when; the city does not record who pulled them.