Converted · ground-floor conversion · Castro/Upper Market
85A Burnett Ave
Completed Mar 2026+1 unit on this lot · now 23 permits
Convert entire first floor into ADU, remove internal circular stair from 1st flr to 2nd flr. Infill flr/clg where stair removed. No other work is required to convert existing space into an ADU. Note: entire 1st flr was existing, unconditioned space prior to 2012. Space was completely built out into.
filed Sep 2025issued Nov 2025 · permit wait 2 monthscompleted Mar 2026 · built in 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$59,425
declared on the ADU permit
Permit wait
2 months
filed → issued
Build time
4 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Convert entire first floor into ADU, remove internal circular stair from 1st flr to 2nd flr. Infill flr/clg where stair removed. No other work is required to convert existing space into an ADU. Note: entire 1st flr was existing, unconditioned space prior to 2012. Space was completely built out into. 202508253800 · Metro Construction INC | filed Sep 2025 · issued Nov 2025 · done Mar 2026 | $59k | city record |
| Electrical | Install 2 recessed lights, inspection of existing conditions for ADU application. EW202511211042 | Nov 21, 2025 → Dec 12, 2025 | — | |
| Plumbing | Work category: 2pa; legalize the kitchen sink, convert the existing space into a ADU. PW20251119690 | Nov 19, 2025 → Dec 15, 2025 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 2719C, lot 020
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.