Metro Construction INC
Named as contractor on 1 ADU project in San Francisco (and 12 permits of any kind). Verify at CSLB before hiring.
ADU projects
1
1 ground-floor conversion
Declared cost (middle half)
$59k
median $59k
Build time
4 months
median, issued → completed
Open · finished
0 · 1
Their ADU projects
- 85A Burnett AveCastro/Upper MarketConverted · ground-floor conversionCompleted3 permitsdeclared $59kfiled Sep 2025permit 2 monthsbuilt 4 months · done Mar 2026ADU permit 202508253800 · city record · flagged ADU by SF DBI
Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.