Rivera Rivas Ivan Alberto
Named as contractor on 1 ADU project in San Francisco (and 21 permits of any kind). Verify at CSLB before hiring.
ADU projects
1
1 legalization
Declared cost (middle half)
$146k
median $146k
Build time
—
median, issued → completed
Open · finished
1 · 0
Their ADU projects
- 4736A 3rd StBayview Hunters PointConverted · legalizationPermit issued, in progress9 permitsdeclared $146k + other workfiled Jan 2023permit 1 year 7 months2 years 3 months since issueADU permit 202301301003 · city record · identified from permit text, two reviewers agree
Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.