J & J Dynamic Construction INC
Named as contractor on 1 ADU project in San Francisco (and 25 permits of any kind). Verify at CSLB before hiring.
ADU projects
1
1 legalization
Declared cost (middle half)
$128k
median $128k
Build time
4 months
median, issued → completed
Open · finished
0 · 1
Their ADU projects
- 281A Castro StCastro/Upper MarketConverted · legalizationCompleted4 permitsdeclared $128kfiled Oct 2025permit 3 monthsbuilt 4 months · done May 2026ADU permit 202510076859 · city record · identified from permit text, two reviewers agree
Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.