Seth Bernstein

License #762514 · not in CSLB's current listworkers’ comp: carriernot on Yelp

Named as contractor on 1 ADU project in San Francisco (and 18 permits of any kind). Verify at CSLB before hiring.

ADU projects
1
1 ground-floor conversion
Declared cost (middle half)
$305k
median $305k
Build time
2 years 9 months
median, issued → completed
Open · finished
0 · 1

Their ADU projects

  1. Converted · ground-floor conversionCompleted11 permitsdeclared $305k
    filed Mar 2021permit 6 monthsbuilt 2 years 9 months · done Jun 2024
    ADU permit 202103176777 · city record · flagged ADU by SF DBI

Each row is one project: the ADU permit plus its revisions, sub-permits and trade permits. Dates are the city’s.